Barrage de la Gileppe Jalhay (B)
|
The original purpose of the dam was to provide usable water for the textile industry in the Verviers area .
A hydroelectric plant was installed that uses the energy of the water drop of 42.9 meters and the flow rate of 76,300 m³/day on average. Two Francis turbines each drive a 320 kW generator . The power plant provides an annual electricity production of 3,300,000 kWh
|
|